Home entrance with an arched dark wood door, stone steps, and a large divided-light window.

Grand Lake's Storefronts and Streets Are Running on the Same 2027 Clock

Walk Lakeshore Avenue on a weekday this fall and you'll pass new concrete bikeway separators along the curb and bus boarding islands taking shape near the lake. The Gap sign at 3277 Lakeshore is gone and the window is covered. Look up and you might see crews replacing the string lights that had been broken over the avenue for years.

These look like separate stories. A city road project, one chain store leaving, and some overdue maintenance. They actually share a deadline. Almost everything changing at Grand Lake's curbs and in its windows right now is aimed at 2027, so this fall is the gap between the avenue the neighborhood had and the one the city and merchants are building.

What's changing Where it stands, fall 2026 Target
Lakeshore Avenue protected bikeway Construction restarted in June after a redesign Early 2027 per the City; spring 2027 per Oaklandside
Lakeshore storefront vacancies Business district set its goal in May 2026 Every vacant storefront filled by 2027
Grand Avenue Complete Streets project Draft detailed designs published Summer 2026 Construction expected to begin Summer 2027

Lakeshore's pavement was in worse shape than the plans assumed

The Lakeshore Avenue project adds nearly a mile of fully protected bike track between East 18th Street and MacArthur Boulevard. Paving began in early February and stopped when crews found the road's base layer was more damaged than expected. Utility investigations then turned up shallow underground conflicts in the work zone, and the city redesigned parts of the base repair to work around them.

That delay moved the finish date repeatedly. In April, the City's project page still showed a "Late Fall 2026" target. By June it said early 2027. Oaklandside put the likely finish at spring 2027. Bike East Bay's September 24 update said the concrete separation and bus islands were taking shape. Full paving and lane striping come next, and work should continue through the end of 2026, weather permitting.

Practically, that means some impacts on the southbound Lakeshore bikeway for a while longer. Riders may use the off-street lakeside trail at a slow pace, passing pedestrians carefully, or ride in the street with traffic. The City has said the walking path along the lake's edge is not affected by the construction.

The street work isn't limited to the roadway. The public parking garage closed briefly this summer so the City could do structural repairs and concrete patching. JLL, one of the garage's managing partners, used the closure to power wash the stairwells and trash enclosures. The string light repairs are something the Lakeshore Avenue Business Improvement District had pushed for over a long stretch. Taken together, the public side of the avenue is being rebuilt from the base layer up to the lights overhead.

The storefronts turned over during the same months

While the street was torn up, several familiar businesses left. LABID's late-July newsletter confirmed that Gap had officially closed after many years on Lakeshore. Over on Grand Avenue, Enssaro moved out of its longtime spot near the lake and opened at 5897 College Avenue in Rockridge on July 31.

The Coffee Mill at 3363 Grand Avenue happened in two steps. In mid-August, Nosh reported that the breakfast spot had closed temporarily for work on the building, with a sign on the door reading "Closed During Construction — Sorry and Thank You." A September 9 roundup then reported that it had shut down after readers spotted "For Lease" signs in the windows. The restaurant first opened on Grand in the mid-1970s, and the same family had owned it for more than 35 years.

Back in May, before Gap's lease ran out, LABID published a list of storefront opportunities in the district:

  • 3413 Lakeshore Avenue
  • 3344 Lakeshore Avenue
  • 3310 Lakeshore Avenue
  • 3277 Lakeshore Avenue, where Gap was expected to close that summer
  • 3270 Lakeshore Avenue
  • 3261 Lakeshore Avenue
  • 470 Lake Park Avenue, the former Starbucks

The district set a goal of filling every one by 2027, working with the City's Economic & Workforce Development Department and the District 2 office. It also ran a public survey asking what people want in those spaces, with options like a café, a specialty market, a bookstore or a family activity space. Local coverage through September had not reported a named incoming tenant for any of these addresses.

The newcomers didn't wait for the cones to come down

The businesses that opened this summer chose to do it in the middle of construction. Mazar Cafe soft-opened on Saturday, July 25, at 2834 Lakeshore Avenue in the former Cafe Lakeview space. It serves Yemeni coffee, drinks and pastries. On July 1, Bar Skula opened at 542 Grand Avenue in the old Sidebar space. It's a seafood-forward bar from the Luka's Taproom team, who describe it as a "remix." By mid-September, Skula had added lunch on Thursdays through Saturdays.

LABID calls Obelisco, at 3407 Lakeshore, one of the avenue's newest arrivals. The family-owned restaurant dates back to 2007 in Oakland and cooks from the traditions of Mexico's Jalisco region.

The merchants also started promoting the avenue together. This summer LABID launched Summer Sips, the first time Lakeshore's restaurants, cafés and bars coordinated special menus and featured drinks, and said more events are coming. On July 27, Golden State Valkyries All-Star Gabby Williams signed autographs at the Lakeshore Peet's. LABID reports that some fans waited in line for as long as three hours. Events like these keep foot traffic on the avenue while the vacancy list waits for tenants.

Grand Avenue is next

As Lakeshore wraps up, Grand Avenue's project is still in design. In Summer 2026, OakDOT released draft detailed designs, which it calls "65% designs," for Grand from Broadway in Uptown to Mandana Boulevard. The biggest change for Grand Lake is between Santa Clara Avenue and Lake Park Avenue and Mandana. That stretch gets a separated bikeway and keeps its front-in angled parking. Parked cars and concrete wheel stops will buffer the bikeway, a two-way center turn lane runs the full segment, and new commercial loading zones give delivery and ride-share drivers curb space so they don't double-park. The City says parking loss will be minimal.

Parklet owners in the Grand Lake District can apply for updated permits, and OakDOT will work with them on designs that meet current standards. In Adams Point, the bikeway will curve out around parklets so they can stay against the curb. Construction is expected to start in Summer 2027 and happen in stages, with exact timing still to be set. Questions and comments go to Charlie Ream at the City. If you want to weigh in while loading zone locations and parklet details are still open, Grand Lake Neighbors meets next on Wednesday, October 21, at 7 p.m. at Barnett Hall.

That means the 2027 overlap is real. Lakeshore's bikeway should be finished around the same time Grand's construction begins, the same year LABID wants Lakeshore's empty storefronts filled.

The longtime anchors through the turnover

While the corners change hands, the Grand Lake Theatre at 3200 Grand turned 100 in March and is still operating as a movie theater. On Lakeshore, Proposition Chicken at 3260 has been open since 2017. Every Monday it gives 10% of dine-in sales to a local nonprofit, and it has donated more than $200,000 to nearly 200 organizations. Lin Jia Asian Kitchen at 3437 has been on the avenue for nearly 15 years. The Cat House Bar at 3255 serves craft cocktails among antique furniture and cat artwork. Bardo at 3343 pairs Michelin-recognized food and drink with live jazz. The Grand Lake Farmers Market sets up at Splash Pad Park every Saturday from 9 a.m. to 2 p.m., all year.

An October Saturday with the cones still up

Weekends are the easiest time to be on Lakeshore during construction. During the summer work phases, the City cleared barriers by the end of each Friday. Here's one way to spend an October Saturday:

  1. Start at the Lake Merritt Sail Boat House at 10 a.m. for a Lake Merritt Institute cleanup. Cleanups happen on Tuesdays and Saturdays.
  2. Walk the lakeside path, which the City has said stays open during construction, to Splash Pad Park for the farmers market. October market days fall on the 3rd, 10th, 17th, 24th and 31st.
  3. Cross Lakeshore and pick up a Yemeni coffee at Mazar Cafe.
  4. End with lunch at Bar Skula on Grand, which serves lunch Thursdays through Saturdays.

For weeknights, the Gardens at Lake Merritt hold Autumn Lights at 666 Bellevue Avenue from October 15 to 17. Oakland Originals premieres three new documentaries at the Grand Lake Theatre on Wednesday, October 7, at 7 p.m., followed by a Q&A with the people featured in the films. The theater's calendar also shows Kupuna ʻĀina with director Q&As on October 20, Minnesota Neighbors with a discussion on October 21, and Hidden Colors 6 on November 4. Since that's a live schedule, check it before you go.

Fall 2027 is when the bikeway, the vacancy goal and Grand Avenue's construction should all be underway or finished. If you're wondering how the street work and storefront changes around Grand Lake might affect your own home, whether you're planning a sale or just thinking about the next few years, DiMaggio Betta Group follows these corridors block by block and is happy to talk it through over coffee at Mazar. Get in Touch.

A Team Invested in Your Success

At DiMaggio Betta Group, luxury isn't defined by a price tag—it's defined by the level of service every client receives. We combine decades of experience, innovative marketing, and personalized strategies to ensure every property receives maximum exposure and every client enjoys a seamless, results-driven experience. Whether you're buying, selling, or investing, we're committed to exceeding expectations at every step.