At the end of Cary Drive, San Leandro Creek finally has new concrete on both banks. The city's October 14 update reported that concrete piles were in on each side of the crossing and that work had begun on the concrete abutments that will hold the new bridge, and the city said it expected to finish them by the end of October 2026. That would finish all the foundation work and get the site ready for the rainy season.
For most of the winter, though, there may be little to see from the street. The next important work happens on paper and in a fabrication shop. The new crossing is a prefabricated weathering steel truss, and it can't be built until its fabrication drawings are fully approved. Neighbors who have walked around the gap since 2023 may see a quiet site this winter, and that matches the schedule.
The city's October 14 project update gives the clearest picture of the order of work.
| Step | Where it happens | Status as of the October 14 update | Estimated time |
|---|---|---|---|
| Concrete piles, both banks | On site | Complete | Done |
| Concrete abutments | On site | Underway | Expected done by end of October 2026 |
| Fabrication drawing review | Designer and fabricator | Comments sent back for revision | One to two more months |
| Truss fabrication | Off site | Can't start until drawings are approved | About three to four months |
| Completion | On site | Forecast | Spring 2027 |
Starting from mid-October, one to two months of drawing review plus three to four months of fabrication leaves little slack before spring. The city has kept spring 2027 as its completion target. The San Leandro Times put it as "late spring" in its October 29 coverage. The October update said the next one was expected the week of November 9. It's a good document to read once the steel drawings are signed off.
Those piles and abutments were a deliberate choice. At a July 10, 2025 Facilities and Transportation Committee meeting, city staff compared two designs. Option 1 reused the old abutments and would have cost about $200,000 less with less disruption. But no one knew the condition of the old foundation, erosion of the creek bank around it was getting worse, and it could only carry a wood or composite wood deck. Option 2 builds new abutments set farther from the eroding bank, on a new foundation that can carry a concrete deck.
The city chose the second approach. Its October announcement and the San Leandro Times both describe new abutments that clear the creek bank and address the scouring seen at the old ones. The replacement will meet current safety and ADA standards. It will have steel handrails with vertical pickets and features meant to discourage riding across, so bicyclists can expect to walk their bikes over the new span.
The old bridge was a single 110-foot span, 7 feet wide, made of steel girders and a concrete deck. According to the city, it was built in 1972. During heavy rain in March 2023, two trees on school district property fell onto it, and it was later removed.
In the weeks after the collapse, neighbors expected the rebuild to come from storm-recovery money. A May 2023 update from the Estudillo Estates Neighborhood Association, posted with its petition to restore the crossing, said there was hope FEMA would pay because the storm caused the damage. It also put the estimated cost at "upwards of 5 million dollars" with no timeline.
That changed on September 3, 2024, when the City Council unanimously accepted a $5 million donation for the replacement, as the San Leandro Times reported that week. In a letter printed in the same issue, Mayor Juan González thanked the Cary Drive/Haas Pedestrian Bridge Association and explained the reason for the gift.
"They recognized that relying on federal assistance could delay bridge reconstruction by a decade, and generously offered $5 million to support the bridge's reconstruction."
The project's costs have come in well below that gift. In July 2025, staff reported a total design cost of $510,457 against a current budget of $1.5 million. On July 20, 2026, the council authorized a $976,775 construction contract with Con-Quest Contractors, Inc. It also allowed change orders up to a combined $293,033. The city describes the donation as dedicated to rebuilding the bridge.
Money was never the slowest part. The crossing touches several properties: school district land on one side, Alameda County Flood Control District land along the creek, and a private parcel. Each one needed its own agreement.
Staff's July 2025 status report showed the work that came before construction. Environmental review and a FEMA floodplain technical memo were each 80% complete, and the civil and structural plans were at 35%. Easement negotiations were still ongoing. The schedule at that point aimed for completion in winter 2026/27.
This fall the pieces finally came together:
The city and the school district then held a groundbreaking. In the city's groundbreaking announcement, SLUSD Board President Jackie Perl called it "what is possible when the City and the School District are committed to a shared goal."
Until the truss is in place, people walking between Cary Drive and Haas Avenue still have to go around. In 2023, the East Bay Times described that trip as a much longer route across Bancroft Lane, one of the area's busiest streets. Neighbors asked about a temporary shortcut from the end of Cary Drive through Bancroft Middle School. The district looked at it and turned it down. It said temporary fencing would weaken campus security, and the path would have crossed the new track, two basketball courts and a newly finished shade structure.
The bridge will reconnect the places it always linked. The city lists Bancroft Middle School, Memorial Park, the San Leandro Main Library at 300 Estudillo Avenue and the businesses along Bancroft Avenue. Until then, here are a few ways to keep tabs on it this winter:
When the truss arrives, crews will set the prefabricated steel span on the new abutments over San Leandro Creek, and that will reopen the route between Cary Drive and Haas Avenue that has been closed since March 2023.
If you live near Estudillo Estates or Bancroft Avenue and want to talk through how projects like the Cary-Haas Bridge fit into your own plans, The DiMaggio Betta Group is always glad to hear from neighbors. Get in Touch.
Stay up to date on the latest real estate trends.
At DiMaggio Betta Group, luxury isn't defined by a price tag—it's defined by the level of service every client receives. We combine decades of experience, innovative marketing, and personalized strategies to ensure every property receives maximum exposure and every client enjoys a seamless, results-driven experience. Whether you're buying, selling, or investing, we're committed to exceeding expectations at every step.